Petrochemical |
Waste Higher Alcohol (WHA) Construction Project
Sector |
Petrochemical |
Project Title |
Waste Higher Alcohol (WHA) Construction Project |
Project Owner |
SABIC |
Client |
Ar-Razi |
Department |
PSD |
Location |
Jubail |
Start Date |
01/11/15 |
End Date |
01/06/17 |
Scope of work |
The project involves procurement, fabrication, modification, construction, testing and commissioning of methanol recovery Waste Higher Alcohol (WHA) side cut unit for plant II. WHA system comprisses of pumps, piping, storage thanks, electrical works, column and exchangers, instrumentation and control system/DCS integration with existing system by adding new hardware and software, civil, firefighting, etc.
|
|
Ar-Razi |
Jubail |
01/11/15 |
01/06/17 |
Mining & Minerals |
Sump Pump – Pipeline Construction Works
Sector |
Mining & Minerals |
Project Title |
Sump Pump – Pipeline Construction Works |
Project Owner |
MA'ADEN |
Client |
Ma'aden Aluminium |
Department |
PSD |
Location |
Jubail |
Start Date |
31/12/15 |
End Date |
01/06/16 |
Scope of work |
The job includes
Pipe line Construction work for Sump Pump Discharge, Fabrication, Erection, Welding, Cutting of pipe, Flange Handling, NDT, Scaffolding above 8 meters.
|
|
Ma'aden Aluminium |
Jubail |
31/12/15 |
01/06/16 |
Petrochemical |
To Supply Scaffolding Services
Sector |
Petrochemical |
Project Title |
To Supply Scaffolding Services |
Project Owner |
SADARA |
Client |
SADARA |
Department |
SCF |
Location |
Jubail |
Start Date |
01/10/15 |
End Date |
01/03/17 |
Scope of work |
The scope of work includes the supplying, rigging, erecting, and dismantling of tower built scaffolding, independent tied scaffolding, suspended scaffolding, cantilevered scaffolding, special scaffolding, mobile tower scaffolding, vessel/column/tank exterior scaffolding, and vessel/ column/tank interior scaffolding, and the provision of scaffolding maintenance services including site cleanup.
|
|
SADARA |
Jubail |
01/10/15 |
01/03/17 |
Petrochemical |
Installation of DEG Aldehyde Removal System (EG-1)
Sector |
Petrochemical |
Project Title |
Installation of DEG Aldehyde Removal System (EG-1) |
Project Owner |
SABIC |
Client |
UNITED |
Department |
PSD |
Location |
Jubail |
Start Date |
01/10/15 |
End Date |
01/04/16 |
Scope of work |
Scope of Work includes Procurement, Designing, Engineering including following activities
Piping Modification for the installation of BED Drum & PSV. Scaffolding, Construction of RCC foundation, Electrical & Instrumentation Work includes Design, Engineering, Supply , Installation and function testing of Rotameter, Pressure Guages, Transmitters, Cable Pulling & Installation of Conduit from new instrument to the existing Ones. Relay setting, Testing & Commissioning.
|
|
UNITED |
Jubail |
01/10/15 |
01/04/16 |
Mining & Minerals |
18% FSA Line & Belt Filter Close Loop Washing Spill Back Line
Sector |
Mining & Minerals |
Project Title |
18% FSA Line & Belt Filter Close Loop Washing Spill Back Line |
Project Owner |
MA'ADEN |
Client |
Ma'aden Phosphate |
Department |
PSD |
Location |
Jubail |
Start Date |
01/03/15 |
End Date |
01/03/17 |
Scope of work |
‘18% FSA Line & Belt Filter Close Loop Washing Spill Back Line
|
|
Ma'aden Phosphate |
Jubail |
01/03/15 |
01/03/17 |
Petrochemical |
Installation of Drum Loading Station
Sector |
Petrochemical |
Project Title |
Installation of Drum Loading Station |
Project Owner |
SABIC |
Client |
UNITED |
Department |
PSD |
Location |
Jubail |
Start Date |
01/10/15 |
End Date |
01/04/16 |
Scope of work |
This project involves all the discipline Mechanical, E & I, Civil, Scaffolding. Fabrication and Erection of Piping and Pipe Supports, Erection of Steel Structure, Fiber Optic Cable and Power Cable Laying, along with Civil, Scaffolding works,
|
|
UNITED |
Jubail |
01/10/15 |
01/04/16 |
Metal |
69649253 Mechanical Installation DEDUSTING / HADEED
Sector |
Metal |
Project Title |
69649253 Mechanical Installation DEDUSTING / HADEED |
Project Owner |
SABIC / HADEED |
Client |
SAUDI VOEST - ALPINE |
Department |
PSD |
Location |
Jubail |
Start Date |
01/07/15 |
End Date |
01/01/16 |
Scope of work |
The poject involves Mechanical Installation Desdusting including Piping, Equipment Erection and Structural Erection works.
|
|
SAUDI VOEST - ALPINE |
Jubail |
01/07/15 |
01/01/16 |
Metal |
69649253 Mechanical Installation MaterialHandling Services
Sector |
Metal |
Project Title |
69649253 Mechanical Installation MaterialHandling Services |
Project Owner |
SABIC / HADEED |
Client |
SAUDI VOEST - ALPINE |
Department |
PSD |
Location |
Jubail |
Start Date |
01/07/15 |
End Date |
01/01/16 |
Scope of work |
The project involves Material Handling Services including Equipment Erection and Structural Erec ction works.
|
|
SAUDI VOEST - ALPINE |
Jubail |
01/07/15 |
01/01/16 |