| Oil & Gas |
NITROGEN PIPELINE UPGRADE ALONG T-183/ T-154
| Sector |
Oil & Gas |
| Project Title |
NITROGEN PIPELINE UPGRADE ALONG T-183/ T-154 |
| Project Owner |
SABIC |
| Client |
Gas Jubail |
| Department |
PSD |
| Location |
Jubail |
| Start Date |
01/02/16 |
| End Date |
01/12/16 |
| Scope of work |
The scope of work includes Procurement/Supply of materials alongwith Fabrication, Construction, Testing and Commissioning support of the pipeline and metering station with all necessary activities for Successful Completion and operation of the Project.
|
|
Gas Jubail |
Jubail |
01/02/16 |
01/12/16 |
| Petrochemical |
Structural Modification to Manturbo Shed
| Sector |
Petrochemical |
| Project Title |
Structural Modification to Manturbo Shed |
| Project Owner |
Advanced Petrochmemical Company |
| Client |
Advanced Petrochmemical Company |
| Department |
PSD |
| Location |
Jubail |
| Start Date |
15/02/16 |
| End Date |
01/09/16 |
| Scope of work |
This project involves Shelter modification and installation of New 25 ton Crane in Regeneration air compressor shelter
|
|
Advanced Petrochmemical Company |
Jubail |
15/02/16 |
01/09/16 |
| Oil & Gas |
CONSTRUCTION OF MAIN WORKS for YANPET/KEMYA Ethane gas Pipeline Delivery System (ARAMCO)
| Sector |
Oil & Gas |
| Project Title |
CONSTRUCTION OF MAIN WORKS for YANPET/KEMYA Ethane gas Pipeline Delivery System (ARAMCO) |
| Project Owner |
Saudi Aramco |
| Client |
DAELIM |
| Department |
CSD |
| Location |
Yanbu |
| Start Date |
01/05/16 |
| End Date |
01/05/17 |
| Scope of work |
CONSTRUCTION OF MAIN WORKS for YANPET/KEMYA Ethane gas Pipeline Delivery System (ARAMCO)
It includes all the related mechanical, electrical, instrumentaiton, low current activities for the successful completion of this project.
|
|
DAELIM |
Yanbu |
01/05/16 |
01/05/17 |
| Petrochemical |
Galvanization of steel structure
| Sector |
Petrochemical |
| Project Title |
Galvanization of steel structure |
| Project Owner |
SADARA |
| Client |
DAELIM |
| Department |
CSD |
| Location |
Jubail |
| Start Date |
01/01/16 |
| End Date |
01/01/16 |
| Scope of work |
Galvanization of Channels, Angles and Steel Plates.
|
|
DAELIM |
Jubail |
01/01/16 |
01/01/16 |
| Oil & Gas |
Requirement of scaffolding and green net
| Sector |
Oil & Gas |
| Project Title |
Requirement of scaffolding and green net |
| Project Owner |
SATORP |
| Client |
SATORP |
| Department |
SCF |
| Location |
Jubail |
| Start Date |
01/01/16 |
| End Date |
01/01/17 |
| Scope of work |
Scaffolding Erection with green net screen installation at transfer tower counterweights and acceleration chutes in critical dust accumulation areas.
|
|
SATORP |
Jubail |
01/01/16 |
01/01/17 |
| Petrochemical |
Replacement of damaged Fiber cable L0541
| Sector |
Petrochemical |
| Project Title |
Replacement of damaged Fiber cable L0541 |
| Project Owner |
SADARA |
| Client |
SADARA |
| Department |
E&I |
| Location |
Jubail |
| Start Date |
01/09/15 |
| End Date |
01/12/15 |
| Scope of work |
Replacement of damaged Fiber cable at SADARA plant.
|
|
SADARA |
Jubail |
01/09/15 |
01/12/15 |
| Metal |
Relocation of Roughing Mill Stand
| Sector |
Metal |
| Project Title |
Relocation of Roughing Mill Stand |
| Project Owner |
SABIC / HADEED |
| Client |
PRIMETALS TECHNOLOGIES |
| Department |
PSD |
| Location |
Jubail |
| Start Date |
01/12/15 |
| End Date |
01/01/16 |
| Scope of work |
Relocation of Roughing Mill Stand
|
|
PRIMETALS TECHNOLOGIES |
Jubail |
01/12/15 |
01/01/16 |
| Petrochemical |
Sump Concrete Walls Repair and Install Steel Liner
| Sector |
Petrochemical |
| Project Title |
Sump Concrete Walls Repair and Install Steel Liner |
| Project Owner |
Saudi Chevron |
| Client |
Saudi Chevron |
| Department |
Civil |
| Location |
Jubail |
| Start Date |
01/01/16 |
| End Date |
13/07/16 |
| Scope of work |
This project involves Removal/Demolition of existing RCC sump pump; Insall steel liner Plates & leak detector tube inside sump; Reinstate top slab with new precast slab & steel plates; Reinstall all affected connections
|
|
Saudi Chevron |
Jubail |
01/01/16 |
13/07/16 |