Petrochemical |
E & I, PHLMS
Sector |
Petrochemical |
Project Title |
E & I, PHLMS |
Project Owner |
SABIC / SAUDI KAYAN |
Client |
SAMSUNG |
Department |
E&I |
Location |
Jubail |
Start Date |
01/04/08 |
End Date |
01/08/09 |
Scope of work |
Electrical & Instrumentation Construction, Testing & Commissioning product handling Warehouse.
|
|
SAMSUNG |
Jubail |
01/04/08 |
01/08/09 |
Petrochemical |
E & I Work at Al-Waha
Sector |
Petrochemical |
Project Title |
E & I Work at Al-Waha |
Project Owner |
AL-WAHA PDH PP PLANT |
Client |
DAELIM |
Department |
E&I |
Location |
Jubail |
Start Date |
01/10/07 |
End Date |
01/01/09 |
Scope of work |
Electrical & Instrumentation Construction at PDH / PP Plant
|
|
DAELIM |
Jubail |
01/10/07 |
01/01/09 |
Petrochemical |
E & I construction of Plant V
Sector |
Petrochemical |
Project Title |
E & I construction of Plant V |
Project Owner |
SABIC / Ar-Razi |
Client |
MHI |
Department |
E&I |
Location |
Jubail |
Start Date |
01/11/05 |
End Date |
01/09/06 |
Scope of work |
E & I Work for the construction of Plant V
|
|
MHI |
Jubail |
01/11/05 |
01/09/06 |
Metal |
Electrical Construction for oxide conveyor
Sector |
Metal |
Project Title |
Electrical Construction for oxide conveyor |
Project Owner |
SABIC / HADEED |
Client |
SAUDI VOEST - ALPINE |
Department |
E&I |
Location |
Jubail |
Start Date |
01/01/01 |
End Date |
01/05/01 |
Scope of work |
Electrical Construction for oxide conveyor
|
|
SAUDI VOEST - ALPINE |
Jubail |
01/01/01 |
01/05/01 |
Metal |
Cold Galvanizing Plant Enhancement
Sector |
Metal |
Project Title |
Cold Galvanizing Plant Enhancement |
Project Owner |
SABIC / HADEED |
Client |
SAUDI VOEST - ALPINE |
Department |
PSD |
Location |
Jubail |
Start Date |
01/01/01 |
End Date |
01/05/01 |
Scope of work |
Electrical & Instrumentation work for Cold Galvanizing plant.
|
|
SAUDI VOEST - ALPINE |
Jubail |
01/01/01 |
01/05/01 |
Metal |
E & I Work for Hot Strip Mill Enhancement
Sector |
Metal |
Project Title |
E & I Work for Hot Strip Mill Enhancement |
Project Owner |
SABIC / HADEED |
Client |
SAUDI VOEST - ALPINE |
Department |
E&I |
Location |
Jubail |
Start Date |
01/01/01 |
End Date |
01/05/01 |
Scope of work |
Complete Eletcrical & Instrumentation for hot strip mill enhancement
|
|
SAUDI VOEST - ALPINE |
Jubail |
01/01/01 |
01/05/01 |
Oil & Gas |
Instrumentation Work
Sector |
Oil & Gas |
Project Title |
Instrumentation Work |
Project Owner |
Saudi Aramco |
Client |
MASDAR |
Department |
Electrical & Instrumentation |
Location |
Jubail |
Start Date |
01/03/98 |
End Date |
01/10/98 |
Scope of work |
Installation of Tank Radar Guage at pump station
|
|
MASDAR |
Jubail |
01/03/98 |
01/10/98 |
Power |
Electrical work
Sector |
Power |
Project Title |
Electrical work |
Project Owner |
SEC |
Client |
SEIMENS |
Department |
E&I |
Location |
Jubail |
Start Date |
01/05/97 |
End Date |
01/07/97 |
Scope of work |
Installation of five 110kV substation
|
|
SEIMENS |
Jubail |
01/05/97 |
01/07/97 |