Oil & Gas |
Instrumentation Installation & commissioning
Sector |
Oil & Gas |
Project Title |
Instrumentation Installation & commissioning |
Project Owner |
SAMSUNG |
Client |
Al-Suwaidi |
Department |
E&I |
Location |
Jubail |
Start Date |
01/03/96 |
End Date |
01/10/96 |
Scope of work |
Complete Instrumentation & Commissioning of PDH & PP Plant
|
|
Al-Suwaidi |
Jubail |
01/03/96 |
01/10/96 |
Metal |
Instrumentation work Utility Centralization & Automation At Hadeed-I
Sector |
Metal |
Project Title |
Instrumentation work Utility Centralization & Automation At Hadeed-I |
Project Owner |
SABIC / HADEED |
Client |
ABB |
Department |
E&I |
Location |
Jubail |
Start Date |
01/08/96 |
End Date |
01/02/97 |
Scope of work |
Centralization & Instrumentation work.
|
|
ABB |
Jubail |
01/08/96 |
01/02/97 |
Oil & Gas |
Electro-Mechanical Work Saudi Aram co Riyadh Refinery.
Sector |
Oil & Gas |
Project Title |
Electro-Mechanical Work Saudi Aram co Riyadh Refinery. |
Project Owner |
Saudi Aramco |
Client |
YUSUF BIN
KANOO |
Department |
Plant Services |
Location |
Riyadh |
Start Date |
01/03/96 |
End Date |
01/12/97 |
Scope of work |
Mechanical & Electrical Construction.
|
|
YUSUF BIN
KANOO |
Riyadh |
01/03/96 |
01/12/97 |
Oil & Gas |
Electrical, Instrumentation & Piping Work for AHG Plant
Sector |
Oil & Gas |
Project Title |
Electrical, Instrumentation & Piping Work for AHG Plant |
Project Owner |
ABDULLAH HASHIM GAS Co. |
Client |
ABDULLAH HASHIM GAS Co. |
Department |
PSD |
Location |
Jubail |
Start Date |
01/01/95 |
End Date |
01/08/95 |
Scope of work |
Electrical, Instrumentation & Piping Work for AHG Plant (Abdullah Hashim Industrial Gases and equipment Company Limited)
|
|
ABDULLAH HASHIM GAS Co. |
Jubail |
01/01/95 |
01/08/95 |
Metal |
Paging System for Saudi Iron & Steel Company.
Sector |
Metal |
Project Title |
Paging System for Saudi Iron & Steel Company. |
Project Owner |
SABIC |
Client |
HADEED |
Department |
E&I |
Location |
Jubail |
Start Date |
01/01/95 |
End Date |
01/07/95 |
Scope of work |
Installation & Commissioning of paging system for Steel Plant.
|
|
HADEED |
Jubail |
01/01/95 |
01/07/95 |
Metal |
Electrical & Instrumentation Work for NAMA Epoxy Company
Sector |
Metal |
Project Title |
Electrical & Instrumentation Work for NAMA Epoxy Company |
Project Owner |
MITSUI ENG & SHIPBUILDING CO. |
Client |
GAMA |
Department |
E&I |
Location |
Jubail |
Start Date |
01/03/96 |
End Date |
01/11/96 |
Scope of work |
Installation & Commissioning of Electrical & Instrumentation
|
|
GAMA |
Jubail |
01/03/96 |
01/11/96 |
Petrochemical |
Electrical & Instrumentation Work For LUBEREF II Plant
Sector |
Petrochemical |
Project Title |
Electrical & Instrumentation Work For LUBEREF II Plant |
Project Owner |
SAUDI SHINWA |
Client |
CHIYODAPETROSTAR Ltd. |
Department |
E&I |
Location |
Yanbu |
Start Date |
01/12/94 |
End Date |
01/03/95 |
Scope of work |
Electrical & Instrumentation
|
|
CHIYODAPETROSTAR Ltd. |
Yanbu |
01/12/94 |
01/03/95 |
Petrochemical |
Fire Protection & Heat Tracing Work
Sector |
Petrochemical |
Project Title |
Fire Protection & Heat Tracing Work |
Project Owner |
CHIYODAPETROSTAR Ltd., |
Client |
CHIYODAPETROSTAR Ltd. |
Department |
E&I |
Location |
Jubail |
Start Date |
01/04/94 |
End Date |
01/09/94 |
Scope of work |
Fire Protection & Heat Tracing for SABIC affiliate
|
|
CHIYODAPETROSTAR Ltd. |
Jubail |
01/04/94 |
01/09/94 |