Petrochemical |
Structure Modification
Sector |
Petrochemical |
Project Title |
Structure Modification |
Project Owner |
TASNEE |
Client |
TASNEE |
Department |
PSD |
Location |
Jubail |
Start Date |
01/01/12 |
End Date |
01/01/12 |
Scope of work |
Installation of Beams at HDPE plant during S/D
|
|
TASNEE |
Jubail |
01/01/12 |
01/01/12 |
Petrochemical |
Fabrication & Installation of various size pipes on existing plant
Sector |
Petrochemical |
Project Title |
Fabrication & Installation of various size pipes on existing plant |
Project Owner |
TASNEE |
Client |
SAMSUNG |
Department |
PSD |
Location |
Jubail |
Start Date |
01/04/12 |
End Date |
01/06/13 |
Scope of work |
Interconnection Piping in Existing Tasnee Plant / Additional GRP Piping scope for Tie-in and Sea Water piping at TASNEE Plant
|
|
SAMSUNG |
Jubail |
01/04/12 |
01/06/13 |
Petrochemical |
SADARA Tank Farm Project for “site office for company and contractor”.
Sector |
Petrochemical |
Project Title |
SADARA Tank Farm Project for “site office for company and contractor”. |
Project Owner |
SADARA |
Client |
DAEWOO |
Department |
Civil |
Location |
Jubail |
Start Date |
01/03/12 |
End Date |
01/08/12 |
Scope of work |
The scope of work includes the construction of “site office for company and contractor”.
|
|
DAEWOO |
Jubail |
01/03/12 |
01/08/12 |
Oil & Gas |
KJO Transfer Function Project
Sector |
Oil & Gas |
Project Title |
KJO Transfer Function Project |
Project Owner |
SAUDI ARAMCO / KJO |
Client |
JGC |
Department |
Civil |
Location |
Khafji |
Start Date |
01/03/12 |
End Date |
01/10/12 |
Scope of work |
Project includes Construction, Civil, Mechanical & Electrical. Works for KJO Transfer Function Project
|
|
JGC |
Khafji |
01/03/12 |
01/10/12 |
Oil & Gas |
Tank Farm E & I Works.
Sector |
Oil & Gas |
Project Title |
Tank Farm E & I Works. |
Project Owner |
SATORP |
Client |
DPL |
Department |
E&I |
Location |
Jubail |
Start Date |
01/12/11 |
End Date |
01/11/12 |
Scope of work |
Electrical & Instrumentation works for Tank Farm Area
|
|
DPL |
Jubail |
01/12/11 |
01/11/12 |
Oil & Gas |
E & I works for Gasoline Package EPC-3 at Yanbu Aramco Sinopec Refining Project-YASREF
Sector |
Oil & Gas |
Project Title |
E & I works for Gasoline Package EPC-3 at Yanbu Aramco Sinopec Refining Project-YASREF |
Project Owner |
Saudi Aramco |
Client |
DAELIM |
Department |
E&I |
Location |
Yanbu |
Start Date |
01/05/11 |
End Date |
01/07/14 |
Scope of work |
E & I Construction works for Package 3 for E & I works for Gasoline Package EPC-3 at Yanbu Aramco Sinopec Refining Project-YASREF
|
|
DAELIM |
Yanbu |
01/05/11 |
01/07/14 |
Oil & Gas |
E & I works for Gasoline Package EPC-4 at Yanbu Aramco Sinopec Refining Project-YASREF
Sector |
Oil & Gas |
Project Title |
E & I works for Gasoline Package EPC-4 at Yanbu Aramco Sinopec Refining Project-YASREF |
Project Owner |
Saudi Aramco |
Client |
DAELIM |
Department |
E&I |
Location |
Yanbu |
Start Date |
01/08/11 |
End Date |
01/07/14 |
Scope of work |
E & I Construction works for Package 4 for E & I works for Gasoline Package EPC-4 at Yanbu Aramco Sinopec Refining Project-YASREF
|
|
DAELIM |
Yanbu |
01/08/11 |
01/07/14 |
Oil & Gas |
UAE, PV Project, Ruwais.
Sector |
Oil & Gas |
Project Title |
UAE, PV Project, Ruwais. |
Project Owner |
TAKREER/ADNOC |
Client |
SHOWA SHELLSEKIYU K. K. |
Department |
E&I |
Location |
UAE |
Start Date |
01/02/11 |
End Date |
01/12/11 |
Scope of work |
Installation &
Commissioning of Photovoltaic System
|
|
SHOWA SHELLSEKIYU K. K. |
UAE |
01/02/11 |
01/12/11 |