MP & LP steam line form utility to UGAA plant
05-23-2020 | Posted inThe project involves installation of MP and LP steam lines from SF2 for UGAA plant, including Design & Detailed Engineering, Procurement of material, Installation of 3" MP steamline & Installation of 4" LP steamline, Scaffolding works, INsulation works, painting, sand blasting, Testing & Commissioning
Read MoreUpgrade of PO4 and Eliminox Pumps
05-23-2020 | Posted inProject involves Detail Design & Engineering, Procurement, Fabrication and Supply of material, Modification of Civl Foundation, piping installation with its fittings and valves, Electrical cables and power supply, DCS for pump connection. Including scope to replace existing chemical injection metering (dosing) of four (4no.) Eliminox and eight (8No.) Phosphates pumps...
Read MoreE & I Work For Aramco COGEN Project
05-23-2020 | Posted inProject involves Electrical, Instrumentation, Installation of Cable Tray, Cable Pulling, Lighting, Instrument Installation, Testing, Loop Checking, Transformer Installation, Transformer Testing, Transformer Commissioning, Switch Gear Panel Installation, Field Panel, Termination, Glanding & Grounding.
Read MoreFire Water Supply Pipelines And Fire Protection System At Jubail Industrial Port (KFIP)
05-23-2020 | Posted inEPC Project(LSTK), Scope of Work Involves Engineering, Complete Procurment & Construction Works Fire protection system at berth-54 & berth-62 Fire protection system Including supply and installation of foam skids (02 Nos.) Fire water supply pipelines including fire hydrants along with the open sea tanker terminal (OSTT), interconnection causeway from current...
Read MoreBenzene Storage Enhancement
05-23-2020 | Posted inEngineering, Procurement & Supply Of Material, Fabrication & Installation (EPC) Of Piping & Equipment. • At two locations (SADAF & SABTANK) Replace the tank bottom in kind with a new one at • Install a leak detection system liner • Install new cathodic protection system. • Contaminated sand beneath tank...
Read MorePMDI & TDI Project(SADARA Isocyanate Project)
05-23-2020 | Posted inScope of Work Includes MCC & Switchgears installation. Low voltage transformers and Power distribution panels installation, Power transformers installation. Testing of switchgear, MCC, transformers including breakers, CT, PT bus bars & various relays.Installation of lighting fixtures. Installation of conduit, cable tray and cable pulling, Cable glanding, termination & testing. Grounding...
Read More