Project: Sub-Contract for Duct Work – El53 Project.
Client: Alfanar
Completion Year: 2017
Prime Contractor:
Scope of Work: Scope of work includes- Intallation of complete HVAC Equipment Including its Accessories, Duct Work,Chilled water pipes, condensate pipes, Cladding, Insulation, Valves and testing & Commissioning at alfanar project site power Plant PP13 DURMAH in Riyadh as per SEC Specifications
Location: Jubail
Scope of work includes-
Intallation of complete HVAC Equipment Including its Accessories, Duct Work,Chilled water pipes, condensate pipes, Cladding, Insulation, Valves and testing & Commissioning at alfanar project site power Plant PP13 DURMAH in Riyadh as per SEC Specifications