Project: Provide service to repair and balancing of the old Turbine rotor for ST-1231
Client: SAHARA
Completion Year: 2019
Prime Contractor:
Scope of Work: Scope of work includes Collect the rotor from Al Waha plant-Jubail. Unload the rotor to a weather protected area. Cleaning of rotor Perform complete dimensional measurements checks of coupling hub area, Bearing DE ,NDE area and Carbon ring DE, NDE packing area. Check the rotor run out. Perform Dye penetrant test.(DPT) . Perform dynamic balancing for rotor (G 2.5)
Location: Jubail
Scope of work includes
Collect the rotor from Al Waha plant-Jubail. Unload the rotor to a weather protected area. Cleaning of rotor
Perform complete dimensional measurements checks of coupling hub area, Bearing DE ,NDE area and Carbon ring DE, NDE packing area. Check the rotor run out. Perform Dye penetrant test.(DPT) . Perform dynamic balancing for rotor (G 2.5)