Project: MISC & MOC EXECUTION WORKS at YASREF Facility
Client: YASREF
Completion Year: 2017
Prime Contractor:
Scope of Work: The project scope includes Pipes and Valve Fittings, Blinding, De-blinding, Measuring, cutting, grinding,welding, threading,pipefitting and installing pipes up to 56" inches diameter, Install and remove valves up to 56" inches diameter, Cold cutting of piping, as required.,Pre and Post Weld Heat Treatment,Painting, Cleaning and Grit Blasting, Insulation Work,Scaffolding - Design, supply, erection, and dismantling of scaffolding. Fireproofing, Rotary Equipment Work, Electrical & Instrumentation Work.
Location: Yanbu
The project scope includes
Pipes and Valve Fittings, Blinding, De-blinding, Measuring, cutting, grinding,welding, threading,pipefitting and installing pipes up to 56″ inches diameter, Install and remove valves up to 56″ inches diameter, Cold cutting of piping, as required.,Pre and Post Weld Heat Treatment,Painting, Cleaning and Grit Blasting, Insulation Work,Scaffolding – Design, supply, erection, and dismantling of scaffolding. Fireproofing, Rotary Equipment Work, Electrical & Instrumentation Work.