Project: Installation of DEG Aldehyde Removal System (EG-1)
Client: UNITED
Completion Year: 2016
Prime Contractor:
Scope of Work: Scope of Work includes Procurement, Designing, Engineering including following activities Piping Modification for the installation of BED Drum & PSV. Scaffolding, Construction of RCC foundation, Electrical & Instrumentation Work includes Design, Engineering, Supply , Installation and function testing of Rotameter, Pressure Guages, Transmitters, Cable Pulling & Installation of Conduit from new instrument to the existing Ones. Relay setting, Testing & Commissioning.
Location: Jubail
Scope of Work includes Procurement, Designing, Engineering including following activities
Piping Modification for the installation of BED Drum & PSV. Scaffolding, Construction of RCC foundation, Electrical & Instrumentation Work includes Design, Engineering, Supply , Installation and function testing of Rotameter, Pressure Guages, Transmitters, Cable Pulling & Installation of Conduit from new instrument to the existing Ones. Relay setting, Testing & Commissioning.