MP & LP steam line form utility to UGAA plant
05-23-2020 | Posted inThe project involves installation of MP and LP steam lines from SF2 for UGAA plant, including Design & Detailed Engineering, Procurement of material, Installation of 3" MP steamline & Installation of 4" LP steamline, Scaffolding works, INsulation works, painting, sand blasting, Testing & Commissioning
Read MoreCooling Water Pump (X-201J-A/B) & U-200J/A) Piping 3D TRACER ONLINE ANALYZERS
05-23-2020 | Posted inProject involves Design, Engineering & Installation of 3D Tracer along with steel structure shed, civil foundation, related PVC piping and E&I work.
Read MorePreventing air entry to Flare Header
05-23-2020 | Posted inProject involves Design, Procurement of Material, Installation of Valves, Testing & Commissioning including Supply and Installation of Valves, Digital JB's (EExd), DI DCS Modules along with Scaffolding activities.
Read MoreEPC PR for Shut off Valve
05-23-2020 | Posted inProject involves Design and Detailed Engineering, Supply of Materials, Installation, Testing and Commissioning to provide Trip Valve with Trip Logic on LP Steam Line going to DIB Re-Boilers along with Cutting, Demolition Piping, Scafolding works, Conduit Installation, Cable Laying,Glanding and Termination.
Read MoreReplace Oxygen Mixing Station with N2 Line
05-23-2020 | Posted inProject involves Supply, Fabrication, Installation, Demolition and Commissioning works for Installation of Oxygen Mixing Station (OMS) with related Nitrogen lines & Valvesin order to maintain the integrity of the OMS system along with associated Nitrogen system.
Read MoreUpgrade of PO4 and Eliminox Pumps
05-23-2020 | Posted inProject involves Detail Design & Engineering, Procurement, Fabrication and Supply of material, Modification of Civl Foundation, piping installation with its fittings and valves, Electrical cables and power supply, DCS for pump connection. Including scope to replace existing chemical injection metering (dosing) of four (4no.) Eliminox and eight (8No.) Phosphates pumps...
Read MoreGeneral Construction Services
05-23-2020 | Posted inThis is a long form contarct which involves Civil & structural works, Pipe works & Valves, Equipment Erection, Mechanical & Electrical Installations, Instrumentation, Painting and Insulation works.
Read MoreScaffolding Erection and Dismantling during PAP T/A 2015
05-23-2020 | Posted inProject involves Scaffolding works during Turn Around 2015 PAP plant.
Read More