Petrochemical |
Fabrication Services for Piping/Valve During ShutDown.
Sector |
Petrochemical |
Project Title |
Fabrication Services for Piping/Valve During ShutDown. |
Project Owner |
CHEMANOL |
Client |
CHEMANOL |
Department |
PSD |
Location |
Jubail |
Start Date |
01/01/13 |
End Date |
01/08/13 |
Scope of work |
Fabrication of Piping, Valve Repair & Replacement
(Mechanical Works)
|
|
CHEMANOL |
Jubail |
01/01/13 |
01/08/13 |
Petrochemical |
Installation of Additional Decanter Unit Project
Sector |
Petrochemical |
Project Title |
Installation of Additional Decanter Unit Project |
Project Owner |
SABIC / SAUDI KAYAN |
Client |
TECNIMONT |
Department |
E&I |
Location |
Jubail |
Start Date |
01/10/12 |
End Date |
01/09/13 |
Scope of work |
Installation Of Decanter, Piping, Equipment Installation.
(Mechanical, Civil, E & I Works)
|
|
TECNIMONT |
Jubail |
01/10/12 |
01/09/13 |
Petrochemical |
MP Steam Line for RA Duct
Sector |
Petrochemical |
Project Title |
MP Steam Line for RA Duct |
Project Owner |
TASNEE |
Client |
TASNEE |
Department |
PSD |
Location |
Jubail |
Start Date |
01/10/12 |
End Date |
01/11/12 |
Scope of work |
Mechanical Works (Man power supply)
|
|
TASNEE |
Jubail |
01/10/12 |
01/11/12 |
Petrochemical |
Design Fabrication & Installation of Ammonia Line between IBB & Al bayroni
Sector |
Petrochemical |
Project Title |
Design Fabrication & Installation of Ammonia Line between IBB & Al bayroni |
Project Owner |
SABIC |
Client |
AL-BAYRONI |
Department |
PSD |
Location |
Jubail |
Start Date |
01/08/12 |
End Date |
01/03/13 |
Scope of work |
Design, Supply, Fabrication, Construction along With Commisioning, (Mechanical, Civil, E & I Works)
|
|
AL-BAYRONI |
Jubail |
01/08/12 |
01/03/13 |
Oil & Gas |
Construction Of Amine Surge Tank & Replacement During S/D.
Sector |
Oil & Gas |
Project Title |
Construction Of Amine Surge Tank & Replacement During S/D. |
Project Owner |
SAMREF |
Client |
SAMREF |
Department |
PSD |
Location |
Yanbu |
Start Date |
01/09/12 |
End Date |
01/07/13 |
Scope of work |
Design, Procurement,
Fabrication & Construction Works
|
|
SAMREF |
Yanbu |
01/09/12 |
01/07/13 |
Oil & Gas |
Repair of Caustic Tank During ShutDown
Sector |
Oil & Gas |
Project Title |
Repair of Caustic Tank During ShutDown |
Project Owner |
SAMREF |
Client |
SAMREF |
Department |
PSD |
Location |
Yanbu |
Start Date |
01/09/12 |
End Date |
01/07/13 |
Scope of work |
Procurement,
Fabrication & Construction Works
|
|
SAMREF |
Yanbu |
01/09/12 |
01/07/13 |
Petrochemical |
Engineering Fabrication and Installation of Handhole & N2 Purging Nozzles
Sector |
Petrochemical |
Project Title |
Engineering Fabrication and Installation of Handhole & N2 Purging Nozzles |
Project Owner |
TASNEE |
Client |
TASNEE |
Department |
PSD |
Location |
Jubail |
Start Date |
01/07/13 |
End Date |
01/07/13 |
Scope of work |
Engineering, Construction. (Mechanical Works)
|
|
TASNEE |
Jubail |
01/07/13 |
01/07/13 |
Petrochemical |
Installation of Fire Fighting System at Tasnee
Sector |
Petrochemical |
Project Title |
Installation of Fire Fighting System at Tasnee |
Project Owner |
TASNEE |
Client |
SAMSUNG |
Department |
PSD |
Location |
Jubail |
Start Date |
01/07/12 |
End Date |
01/02/13 |
Scope of work |
Supply, Contruction work Like Piping/ Repair welding 7 Painting & NDT, (Mechanical Works)
|
|
SAMSUNG |
Jubail |
01/07/12 |
01/02/13 |