Petrochemical |
Site work installation of Air Comp Unit
Sector |
Petrochemical |
Project Title |
Site work installation of Air Comp Unit |
Project Owner |
SABIC |
Client |
Ar-Razi |
Department |
PSD |
Location |
Jubail |
Start Date |
01/03/14 |
End Date |
01/12/14 |
Scope of work |
EPC job involves Removal / Re-installation of Air Compressor & Auxillaries along with some fabrication & modification work.
|
|
Ar-Razi |
Jubail |
01/03/14 |
01/12/14 |
Petrochemical |
Installation of Toluene Drain Line from Vessel-3460 to Column-3610
Sector |
Petrochemical |
Project Title |
Installation of Toluene Drain Line from Vessel-3460 to Column-3610 |
Project Owner |
SABIC |
Client |
UNITED |
Department |
PSD |
Location |
Jubail |
Start Date |
01/03/14 |
End Date |
01/08/14 |
Scope of work |
Mechanical work, Toluene drain line to be installed, EPC job for the Installation of Toluene Drain Line from Vessel-3460 to Column-3610 Project.
|
|
UNITED |
Jubail |
01/03/14 |
01/08/14 |
Petrochemical |
PR for LSTK Contract to Provide isolation valve on each exchanger E-2322A/B/C LSTK
Sector |
Petrochemical |
Project Title |
PR for LSTK Contract to Provide isolation valve on each exchanger E-2322A/B/C LSTK |
Project Owner |
SABIC |
Client |
UNITED |
Department |
PSD |
Location |
Jubail |
Start Date |
01/03/14 |
End Date |
01/08/14 |
Scope of work |
LSTK job involving detailed Engineering, Procurement of long lead items. Mechanical works Such as Valve, removal and Re-installation, commissioning, testing along with modification of associate piping.
|
|
UNITED |
Jubail |
01/03/14 |
01/08/14 |
Petrochemical |
Install Life Line at PE Bulk Loading
Sector |
Petrochemical |
Project Title |
Install Life Line at PE Bulk Loading |
Project Owner |
Tasnee |
Client |
Tasnee |
Department |
PSD |
Location |
Jubail |
Start Date |
01/05/14 |
End Date |
01/07/14 |
Scope of work |
Mechanical work along with installation of structure as life line for working for the Install Life Line at PE Bulk Loading Project at Tasnee
|
|
Tasnee |
Jubail |
01/05/14 |
01/07/14 |
Petrochemical |
Diversion of Cooling Water Outlets to the fire water Tank
Sector |
Petrochemical |
Project Title |
Diversion of Cooling Water Outlets to the fire water Tank |
Project Owner |
Tasnee |
Client |
Tasnee |
Department |
PSD |
Location |
Jubail |
Start Date |
01/10/14 |
End Date |
01/11/14 |
Scope of work |
Supply, Fabrication and Erection of Piping Material and Steel Structure Supports Fabrication Works and Civil works.
|
|
Tasnee |
Jubail |
01/10/14 |
01/11/14 |
Petrochemical |
Replacement of Heat Exchangers 2E-1407 A/B & Associated Piping Works
Sector |
Petrochemical |
Project Title |
Replacement of Heat Exchangers 2E-1407 A/B & Associated Piping Works |
Project Owner |
SABIC |
Client |
SHARQ |
Department |
PSD |
Location |
Jubail |
Start Date |
01/04/14 |
End Date |
01/04/14 |
Scope of work |
The project includes Replacement of Heat Exchangers 2E-1407 A/B & Associated Piping Works during the TAM.
|
|
SHARQ |
Jubail |
01/04/14 |
01/04/14 |
Oil & Gas |
Fire Water Supply Pipelines And Fire Protection System At Jubail Industrial Port (KFIP)
Sector |
Oil & Gas |
Project Title |
Fire Water Supply Pipelines And Fire Protection System At Jubail Industrial Port (KFIP) |
Project Owner |
SATORP |
Client |
SATORP |
Department |
PSD |
Location |
Jubail |
Start Date |
01/03/14 |
End Date |
01/10/16 |
Scope of work |
EPC Project(LSTK), Scope of Work Involves Engineering, Complete Procurment & Construction Works
Fire protection system at berth-54 & berth-62
Fire protection system Including supply and installation of foam skids (02 Nos.)
Fire water supply pipelines including fire hydrants along with the open sea tanker terminal (OSTT), interconnection causeway from current terminating point at berth-61 to berth-62.
Potable water supply line extended from berth-61 to berth-62 and terminated to the water utility system at berth-62.
Installation of a new multiplexer RTU at berth-62.
Also involves very Sophisticated Scaffoldding.
|
|
SATORP |
Jubail |
01/03/14 |
01/10/16 |
Metal |
Replacement of middle burden feeder shaft.
Sector |
Metal |
Project Title |
Replacement of middle burden feeder shaft. |
Project Owner |
SABIC |
Client |
HADEED |
Department |
PSD |
Location |
Jubail |
Start Date |
01/01/14 |
End Date |
01/04/14 |
Scope of work |
Mechanical Works, removal and re-installation of new Middle burden Shaft at Hadeed plant.
|
|
HADEED |
Jubail |
01/01/14 |
01/04/14 |