Oil & Gas |
Install Manual Block Valve at Ph-7 filter
Sector |
Oil & Gas |
Project Title |
Install Manual Block Valve at Ph-7 filter |
Project Owner |
SABIC |
Client |
Gas Jubail |
Department |
PSD |
Location |
Jubail |
Start Date |
01/04/14 |
End Date |
01/05/14 |
Scope of work |
Removal and Re-installation of manual block valve / isolation valve at Phase 7 Filter
|
|
Gas Jubail |
Jubail |
01/04/14 |
01/05/14 |
Oil & Gas |
Ph-8 GOX Pipeline Material Replacement
Sector |
Oil & Gas |
Project Title |
Ph-8 GOX Pipeline Material Replacement |
Project Owner |
SABIC |
Client |
Gas Jubail |
Department |
PSD |
Location |
Jubail |
Start Date |
01/04/14 |
End Date |
01/05/14 |
Scope of work |
Replacement of existing CS pipe and 02 Nos. with elbows of Monel material during the Ph-8 GOX Pipeline Material Replacement Project
|
|
Gas Jubail |
Jubail |
01/04/14 |
01/05/14 |
Petrochemical |
Site work installation of Air Comp Unit
Sector |
Petrochemical |
Project Title |
Site work installation of Air Comp Unit |
Project Owner |
SABIC |
Client |
Ar-Razi |
Department |
PSD |
Location |
Jubail |
Start Date |
01/03/14 |
End Date |
01/12/14 |
Scope of work |
EPC job involves Removal / Re-installation of Air Compressor & Auxillaries along with some fabrication & modification work.
|
|
Ar-Razi |
Jubail |
01/03/14 |
01/12/14 |
Petrochemical |
Installation of Toluene Drain Line from Vessel-3460 to Column-3610
Sector |
Petrochemical |
Project Title |
Installation of Toluene Drain Line from Vessel-3460 to Column-3610 |
Project Owner |
SABIC |
Client |
UNITED |
Department |
PSD |
Location |
Jubail |
Start Date |
01/03/14 |
End Date |
01/08/14 |
Scope of work |
Mechanical work, Toluene drain line to be installed, EPC job for the Installation of Toluene Drain Line from Vessel-3460 to Column-3610 Project.
|
|
UNITED |
Jubail |
01/03/14 |
01/08/14 |
Petrochemical |
PR for LSTK Contract to Provide isolation valve on each exchanger E-2322A/B/C LSTK
Sector |
Petrochemical |
Project Title |
PR for LSTK Contract to Provide isolation valve on each exchanger E-2322A/B/C LSTK |
Project Owner |
SABIC |
Client |
UNITED |
Department |
PSD |
Location |
Jubail |
Start Date |
01/03/14 |
End Date |
01/08/14 |
Scope of work |
LSTK job involving detailed Engineering, Procurement of long lead items. Mechanical works Such as Valve, removal and Re-installation, commissioning, testing along with modification of associate piping.
|
|
UNITED |
Jubail |
01/03/14 |
01/08/14 |
Petrochemical |
Install Life Line at PE Bulk Loading
Sector |
Petrochemical |
Project Title |
Install Life Line at PE Bulk Loading |
Project Owner |
Tasnee |
Client |
Tasnee |
Department |
PSD |
Location |
Jubail |
Start Date |
01/05/14 |
End Date |
01/07/14 |
Scope of work |
Mechanical work along with installation of structure as life line for working for the Install Life Line at PE Bulk Loading Project at Tasnee
|
|
Tasnee |
Jubail |
01/05/14 |
01/07/14 |
Petrochemical |
Diversion of Cooling Water Outlets to the fire water Tank
Sector |
Petrochemical |
Project Title |
Diversion of Cooling Water Outlets to the fire water Tank |
Project Owner |
Tasnee |
Client |
Tasnee |
Department |
PSD |
Location |
Jubail |
Start Date |
01/10/14 |
End Date |
01/11/14 |
Scope of work |
Supply, Fabrication and Erection of Piping Material and Steel Structure Supports Fabrication Works and Civil works.
|
|
Tasnee |
Jubail |
01/10/14 |
01/11/14 |
Petrochemical |
Replacement of Heat Exchangers 2E-1407 A/B & Associated Piping Works
Sector |
Petrochemical |
Project Title |
Replacement of Heat Exchangers 2E-1407 A/B & Associated Piping Works |
Project Owner |
SABIC |
Client |
SHARQ |
Department |
PSD |
Location |
Jubail |
Start Date |
01/04/14 |
End Date |
01/04/14 |
Scope of work |
The project includes Replacement of Heat Exchangers 2E-1407 A/B & Associated Piping Works during the TAM.
|
|
SHARQ |
Jubail |
01/04/14 |
01/04/14 |