Petrochemical |
INSTALLATION OF SECURITY LIGHTING POST FOR DAELIM KEMYA
Sector |
Petrochemical |
Project Title |
INSTALLATION OF SECURITY LIGHTING POST FOR DAELIM KEMYA |
Project Owner |
SABIC / KEMYA |
Client |
DAELIM |
Department |
----- |
Location |
Jubail |
Start Date |
01/09/16 |
End Date |
01/11/16 |
Scope of work |
The Scope of Work includes
Mobilization of necessary manpower, equipment, tools & consurnables.
Installation of 40 Sets Security Fencing Lighting Post,
Cable Pulling with Termination, & Steel Support Fabrication
|
|
DAELIM |
Jubail |
01/09/16 |
01/11/16 |
Petrochemical |
CIVIL MAINTENANCE SERVICES – (ITB-CON-S023)
Sector |
Petrochemical |
Project Title |
CIVIL MAINTENANCE SERVICES – (ITB-CON-S023) |
Project Owner |
SIPCHEM |
Client |
SIPCHEM |
Department |
----- |
Location |
Jubail |
Start Date |
01/06/16 |
End Date |
01/06/19 |
Scope of work |
This is a long form contract (LFC) For 3 Years and Extendable. The Project Includes
Excavation, Backfilling Including Compaction, Concreting Works (Includes Mixing, Pouring/Placing And Curing), Grouting, Water Proofing, Finishing, Supply And Install (PVC And GI Pipes For Cold And Hot Water Supply With All Corresponding Fittings, Tiles And Marbles Includes Adhesives, Skirting, Electrical Fixtures And Accessories, Doors And Windows With Complete Accessories).
|
|
SIPCHEM |
Jubail |
01/06/16 |
01/06/19 |
Oil & Gas |
Main Construction Service for GAS PHASE IV (DBN) Debottlenecking Project
Sector |
Oil & Gas |
Project Title |
Main Construction Service for GAS PHASE IV (DBN) Debottlenecking Project |
Project Owner |
SABIC / Gas Jubail |
Client |
WISON |
Department |
----- |
Location |
Jubail |
Start Date |
01/07/16 |
End Date |
01/07/17 |
Scope of work |
The Scope of work includes:
Demolishing the existing facilities and installation of mechanical equipment (including modification).
fabrication defect or field design changes, as needed, Assembly of steelwork, using bolted and welded connections, Modification of related existing structural steel,Piping and support fabrication and installation, testing and cleaning (including Tie-in), Civil and foundation work, Demolition and installation of E&I facility, Electrical equipment modification, erection and test, Instrument installation, calibration and loop testing, Cable rack and tray installation. Electrical and instrument cable pulling, termination, Inspection and testing.
Support during Commissioning and Startup.
|
|
WISON |
Jubail |
01/07/16 |
01/07/17 |
Petrochemical |
Structural support inspection and repair
Sector |
Petrochemical |
Project Title |
Structural support inspection and repair |
Project Owner |
SABIC |
Client |
IBN-SINA |
Department |
----- |
Location |
Jubail |
Start Date |
01/10/15 |
End Date |
01/06/16 |
Scope of work |
The Scope of Work Includes
Structural support inspection and repair workat IBN SINA, To provide of supervisors, Permit receivers, man / fire watch, welders, safety officers, fabricators/ pipe fitters, NDT technicians, QA/QC inspector & riggers.
|
|
IBN-SINA |
Jubail |
01/10/15 |
01/06/16 |
Petrochemical |
Revamp Of Bagging Machine at PPS
Sector |
Petrochemical |
Project Title |
Revamp Of Bagging Machine at PPS |
Project Owner |
SABIC |
Client |
PetroKemya |
Department |
----- |
Location |
Jubail |
Start Date |
01/05/16 |
End Date |
01/06/16 |
Scope of work |
The Scope of Work Includes
Engineering(Design and engineering for tie inns of pneumatic piping, to pump, then pump to machine),
Procurement( Supply with Engineering for revamping Vacuum Pump for Bag opening System to replace with existing venture stem, Weighing contrroller upgrading)., Construction and assistance in commissioning
|
|
PetroKemya |
Jubail |
01/05/16 |
01/06/16 |
Oil & Gas |
Repairing of Fiber Optic Cable at KM 11
Sector |
Oil & Gas |
Project Title |
Repairing of Fiber Optic Cable at KM 11 |
Project Owner |
SATORP |
Client |
SATORP |
Department |
----- |
Location |
Jubail |
Start Date |
01/05/16 |
End Date |
01/06/16 |
Scope of work |
The Scope of Work Includes
Checking of Existing Condition of Fibre optic Cable, Fusion splicing of damaged Parts which include Stripping the fibre by remiving protective coationg, cleaning, Cleaving, Splicing & Testing of Fibre optic Cable.To supply all manpower, equipment & tools(like fusion splicer, optical source beam, power meter, OTDR etc) for the job.
|
|
SATORP |
Jubail |
01/05/16 |
01/06/16 |
Petrochemical |
MECH Support services for 3TPS-20
Sector |
Petrochemical |
Project Title |
MECH Support services for 3TPS-20 |
Project Owner |
SABIC |
Client |
SHARQ |
Department |
----- |
Location |
Jubail |
Start Date |
05/05/16 |
End Date |
01/01/17 |
Scope of work |
The Scope of Work Includes
Removing and installing of pressure safety valves (PSV) 2. Connecting and disconnecting of pipelines. 3. Filters and strainers cleaning / replacement 4. Gaskets replacement 5. Removing and installing valves including “instrument valves” 6. Cutter knife replacement 7. Greasing and change / add oil activities 8. Pumps, blowers and compressors overhauling support 9. Rotary valves overhauling support 10. Remove and install heat exchangers covers 11. Pelletizer, FCM, LCM, gearboxes overhauling support 12. Bolts tightening 13. Blinding and de-blinding activities 14. Flexible hoses replacement 15. De-coupling, alignment and coupling for rotary equipment
|
|
SHARQ |
Jubail |
05/05/16 |
01/01/17 |
Power |
Sub-Contract for Duct Work – El53 Project.
Sector |
Power |
Project Title |
Sub-Contract for Duct Work – El53 Project. |
Project Owner |
SEC |
Client |
Alfanar |
Department |
----- |
Location |
Jubail |
Start Date |
01/04/16 |
End Date |
01/09/17 |
Scope of work |
Scope of work includes-
Intallation of complete HVAC Equipment Including its Accessories, Duct Work,Chilled water pipes, condensate pipes, Cladding, Insulation, Valves and testing & Commissioning at alfanar project site power Plant PP13 DURMAH in Riyadh as per SEC Specifications
|
|
Alfanar |
Jubail |
01/04/16 |
01/09/17 |