Petrochemical |
LHS Drumming Line in Packaging Centre to provide Electrical Heat Tracing Services
Sector |
Petrochemical |
Project Title |
LHS Drumming Line in Packaging Centre to provide Electrical Heat Tracing Services |
Project Owner |
SADARA |
Client |
SADARA |
Department |
----- |
Location |
Jubail |
Start Date |
01/06/17 |
End Date |
01/09/17 |
Scope of work |
Scope of Works includes.
Installation of Heating Cable (Self-Regulating Type) on newly installed Pipeline, Power Junction Box & Accessories, RTD Sensor, End & Splice Termination Kit, Inline Splice Kit, Fiber Tape. Installation different sizes of Conduit. Installation of Power & RTD cable from EHT Panel at MCC to field. Cable glanding and termination
|
|
SADARA |
Jubail |
01/06/17 |
01/09/17 |
Petrochemical |
Modifications to Combined Pyoil to Fluxoil Line to MFC-Heat Tracing Services
Sector |
Petrochemical |
Project Title |
Modifications to Combined Pyoil to Fluxoil Line to MFC-Heat Tracing Services |
Project Owner |
SADARA |
Client |
SADARA |
Department |
----- |
Location |
Jubail |
Start Date |
01/06/17 |
End Date |
01/12/17 |
Scope of work |
Scope of Works includes.
Installation of Heating Cable, Power Junction Box & Accessories, RTD Sensor, End & Splice Termination Kit,
Fiber Tape, cable tray, power & RTD cable, Cable glanding and termination.
|
|
SADARA |
Jubail |
01/06/17 |
01/12/17 |
Petrochemical |
CGC 30″ Line Partially Replacement Service
Sector |
Petrochemical |
Project Title |
CGC 30″ Line Partially Replacement Service |
Project Owner |
SABIC |
Client |
Sharq |
Department |
----- |
Location |
Jubail |
Start Date |
01/05/17 |
End Date |
01/07/17 |
Scope of work |
Scope of work includes.
Fabrication & Erection of piping & Pipe supports. NDT, Painting and sandblasting, testing and pre-commissioning and commissioning support.
|
|
Sharq |
Jubail |
01/05/17 |
01/07/17 |
Petrochemical |
Electric Heat Tracing System Installation (ATR R5201) PV TAM17
Sector |
Petrochemical |
Project Title |
Electric Heat Tracing System Installation (ATR R5201) PV TAM17 |
Project Owner |
SABIC |
Client |
Ar-Razi |
Department |
----- |
Location |
Jubail |
Start Date |
01/04/17 |
End Date |
01/08/17 |
Scope of work |
Scope of works includes.
Removal of insulation cladding and existing heat tracing cable from 14″ as per drawing .
Installation of Heat tracing cable, cable glanding and termination, cable continuity checking and installation of insulation and cladding
|
|
Ar-Razi |
Jubail |
01/04/17 |
01/08/17 |
Oil & Gas |
Trial Excavation Works for Replace Boilers at Berri Gas Plant
Sector |
Oil & Gas |
Project Title |
Trial Excavation Works for Replace Boilers at Berri Gas Plant |
Project Owner |
Saudi Aramco |
Client |
JGC |
Department |
----- |
Location |
Jubail |
Start Date |
01/05/17 |
End Date |
01/06/17 |
Scope of work |
Scope of works includes
Demolition & Disposal od existing concrete slab / asphalt pavement. Trial excavation works. Backfilling using excavated soil & cleaning. Reinstallation of pavement.
|
|
JGC |
Jubail |
01/05/17 |
01/06/17 |
Oil & Gas |
Piping works for Gas Jubail project
Sector |
Oil & Gas |
Project Title |
Piping works for Gas Jubail project |
Project Owner |
SABIC / Gas Jubail |
Client |
eTEC Arabia |
Department |
----- |
Location |
Jubail |
Start Date |
01/03/17 |
End Date |
01/04/17 |
Scope of work |
Scope of work includes. Scaffolding installation and removal, FRP Piping installation and jointing and hydrotest.
|
|
eTEC Arabia |
Jubail |
01/03/17 |
01/04/17 |
Petrochemical |
Civil Works for Washing Facility for Clean Room
Sector |
Petrochemical |
Project Title |
Civil Works for Washing Facility for Clean Room |
Project Owner |
Sipchem |
Client |
Sipchem |
Department |
----- |
Location |
Jubail |
Start Date |
01/03/17 |
End Date |
01/04/17 |
Scope of work |
Civil Works for Washing Facility for Clean Room at the Sipchem plant.
|
|
Sipchem |
Jubail |
01/03/17 |
01/04/17 |
Power |
Transformer Dismantling, Lifting and mobility services at Khulais S/S
Sector |
Power |
Project Title |
Transformer Dismantling, Lifting and mobility services at Khulais S/S |
Project Owner |
SEC |
Client |
Fuji Electric |
Department |
----- |
Location |
Jeddah |
Start Date |
01/03/17 |
End Date |
01/04/17 |
Scope of work |
Scope of work includes
Inspection of 250 MVA Transformer at Workshop, including dismantling, Loading, Transportation from Khulais S/S to workshop
|
|
Fuji Electric |
Jeddah |
01/03/17 |
01/04/17 |