Petrochemical |
Restore the (RG) Vent Line Movement from Support in Plant II ESD (Emergency)
Sector |
Petrochemical |
Project Title |
Restore the (RG) Vent Line Movement from Support in Plant II ESD (Emergency) |
Project Owner |
SABIC |
Client |
Ar-Razi |
Department |
----- |
Location |
Jubail |
Start Date |
14/12/17 |
End Date |
14/12/17 |
Scope of work |
The project scope is to carry out the emergency work for RG Vent Line Rectification works in Plant-II ESD. It includes rectification of 24” line by cutting at joints and rectification of pipe support and damaged structure along with provision of all necessary material to complete the job.
|
|
Ar-Razi |
Jubail |
14/12/17 |
14/12/17 |
Oil & Gas |
Bolt Torque for Khuff Gas Shut Down
Sector |
Oil & Gas |
Project Title |
Bolt Torque for Khuff Gas Shut Down |
Project Owner |
Saudi Aramco |
Client |
Uthmaniyah Gas Plant |
Department |
----- |
Location |
Uthmaniyah |
Start Date |
10/01/18 |
End Date |
01/01/18 |
Scope of work |
Provision of Hydraulic bolt tightening (torque machine) to loosen and tighten the bolts at Inlet Area during shut down.
|
|
Uthmaniyah Gas Plant |
Uthmaniyah |
10/01/18 |
01/01/18 |
Oil & Gas |
Bolt Tensioning & Torquing Services (for the period of 10 years + 2 years extension option)
Sector |
Oil & Gas |
Project Title |
Bolt Tensioning & Torquing Services (for the period of 10 years + 2 years extension option) |
Project Owner |
Petro Rabigh |
Client |
Petro Rabigh |
Department |
----- |
Location |
Yanbu |
Start Date |
01/12/17 |
End Date |
01/12/27 |
Scope of work |
The scope includes bolt tensioning, bolt torqueing, un-bolting (loosening of bolts), on-site machining, flange facing, flange spreading, pipe cutting, end prepping, on-line valve testing requirements.
|
|
Petro Rabigh |
Yanbu |
01/12/17 |
01/12/27 |
Petrochemical |
Rental of Blast Resistant Modules (BRMs) for SCP/JCP TA 2018
Sector |
Petrochemical |
Project Title |
Rental of Blast Resistant Modules (BRMs) for SCP/JCP TA 2018 |
Project Owner |
Saudi Chevron |
Client |
Saudi Chevron |
Department |
----- |
Location |
Jubail |
Start Date |
06/11/17 |
End Date |
01/02/18 |
Scope of work |
It includes provision of 17 no’s of Blast Resistant Modules (BRMs), supply and instalation of Power Generators, Furniture for 04 workstations, elcetrical, HVAC and all Distribution Panels for combines BRMs.
|
|
Saudi Chevron |
Jubail |
06/11/17 |
01/02/18 |
Power |
Site Training of 67 MVA 132 kV Class Power Transformers
Sector |
Power |
Project Title |
Site Training of 67 MVA 132 kV Class Power Transformers |
Project Owner |
Bandariyah Int'l Co. |
Client |
Bandariyah Int'l Co. |
Department |
----- |
Location |
Al-Kharj |
Start Date |
15/05/17 |
End Date |
15/05/17 |
Scope of work |
The scope includes provision of Site Training on EFACEC 67MVA, 110/13.8kV Power Transformers at New South Industrial Substation at Al-Kharj
|
|
Bandariyah Int'l Co. |
Al-Kharj |
15/05/17 |
15/05/17 |
Petrochemical |
Electrical Power Equipment Service
Sector |
Petrochemical |
Project Title |
Electrical Power Equipment Service |
Project Owner |
SABIC |
Client |
Sabtank Jubail |
Department |
----- |
Location |
Jubail |
Start Date |
28/08/17 |
End Date |
28/08/18 |
Scope of work |
The scope includes Electric Power Equipment Major Preventive maintenance, testing & emergency support. It shall include also any corrective maintenance arises from these activities. The services to be performed in KFIP Port/ Sabtank Facilities area PCQ1.
|
|
Sabtank Jubail |
Jubail |
28/08/17 |
28/08/18 |
Oil & Gas |
Instrument Cable Testing works for Field Pipelines and Sitra Storage Expansion Project in BGP
Sector |
Oil & Gas |
Project Title |
Instrument Cable Testing works for Field Pipelines and Sitra Storage Expansion Project in BGP |
Project Owner |
SAUDI ARAMCO / BGP |
Client |
JGC |
Department |
----- |
Location |
Jubail |
Start Date |
07/09/17 |
End Date |
09/10/17 |
Scope of work |
The scope covers Instrument Cable Testing for major Instrument Equipment such as Visual inspection of all wiring connected to Junction box, verification of cable connections, field grounding, proper cable dressing along-with insulation resistance, conductor resisitance and continuity tests.
|
|
JGC |
Jubail |
07/09/17 |
09/10/17 |
Oil & Gas |
Overspeed Trip Relays Relocation PH8 Expanders 81-ET-001 AB/002
Sector |
Oil & Gas |
Project Title |
Overspeed Trip Relays Relocation PH8 Expanders 81-ET-001 AB/002 |
Project Owner |
SABIC |
Client |
Gas Jubail |
Department |
----- |
Location |
Jubail |
Start Date |
06/12/17 |
End Date |
01/01/18 |
Scope of work |
The scope includes supply, installation, testing and commissioning of PILZ Relays, Instrument cables and conduit pipes for Expander Overspeed Trip Relay Relocation in Gas Jubail.
|
|
Gas Jubail |
Jubail |
06/12/17 |
01/01/18 |