Project: Install a stand by pump and level indication for storm water Lagoon
Client: SAFCO
Completion Year: 2016
Prime Contractor:
Scope of Work: The project scope includes installation of standby pump and level indication in storm water lagoon. The brief scope of work is as below: Design and detail engineering for installation of standby pump and level indicator, Procurement of pump, level transmitter, control panel, pipe, pipe fittings, and cables, Construction of civil foundation, rerouting of UPVC pipe and curb wall around pump area,Installation of new pump foundation.,Modification of SS piping. Installation of new piping, valves and strainer.,Installation of new radar level transmitter.,Installation of new control panel.,Installation of cables.,Scaffolding erection.,Testing, commissioning and DCS configuration
Location: Jubail
The project scope includes installation of standby pump and level indication in storm water lagoon. The brief scope of work is as below:
Design and detail engineering for installation of standby pump and level indicator, Procurement of pump, level transmitter, control panel, pipe, pipe fittings, and cables, Construction of civil foundation, rerouting of UPVC pipe and curb wall around pump area,Installation of new pump foundation.,Modification of SS piping.
Installation of new piping, valves and strainer.,Installation of new radar level transmitter.,Installation of new control panel.,Installation of cables.,Scaffolding erection.,Testing, commissioning and DCS configuration