Project: Inspection and Repairing of 4 MVA Transformer at Arar Power Plant Extensıon IV Project
Client: BEST Transformer
Completion Year: 2017
Prime Contractor:
Scope of Work: Scope of Work includes 4 MVA, 4.16/0.48KV Transformer inspection, electrical testing, gasket replacement, oil filtration and filling work & Oil Sampling and Oil Testing.
Location: ARAR
Scope of Work includes
4 MVA, 4.16/0.48KV Transformer inspection, electrical testing, gasket
replacement, oil filtration and filling work & Oil Sampling and Oil Testing.