OUR PROJECTS

Join the tide to build the future

Projects > Our Project

Petrochemicals

RIK 34E35A Heat Exchangers EDC plant

RIK 34E35A Heat Exchangers EDC plant

Client : SABIC (SADAF)

Prime Contractor : SABIC (SADAF)

Disciplines : RIK 34E35A Heat Exchangers EDC plant

Location : Jubail. KSA

Completion : November 2018

Scope of Work : The project scope includes Procurement of material, Fabrication, Testing and Supply and installation of Heat Exchanger. Fabrication of Heat Exchanger, NDT and Hydro-Testing of Heat Exchanger.

SABIC (SADAF)

Jubail. KSA

November 2018

Mining & Minerals

General Construction Services RFP Contract (LFC)

General Construction Services RFP Contract (LFC)

Client : MAADEN (Ma'aden Aluminium)

Prime Contractor : MAADEN (Ma'aden Aluminium)

Disciplines : General Construction Services RFP Contract (LFC)

Location : Ras Al Khair, KSA

Completion : July, 2022

Scope of Work : "The project scope is to execute the General services contract for MAADEN Aluminium
for 3 years. The major works included in this contract are as under, procurement, Fabrication, installation, precommissioning, commissioning etc. for various discipline, Civil & Structure Works, Piping Works & Equipment Works, Electrical works & Instrumentation & control Systems, DCS, Painting & Insulation, Scaffolding Works"

MAADEN (Ma'aden Aluminium)

Ras Al Khair, KSA

July, 2022

Petrochemicals

RIK for Tube Bundle - Ethane Recycle Emergency Heater 11E114 at Ethylene Plant

RIK for Tube Bundle - Ethane Recycle Emergency Heater 11E114 at Ethylene Plant

Client : SABIC (Sadaf)

Prime Contractor : SABIC (Sadaf)

Disciplines : RIK for Tube Bundle – Ethane Recycle Emergency Heater 11E114 at Ethylene Plant

Location : Jubail, KSA

Completion : October, 2019

Scope of Work : "The project scope is Procurement of materials, fabrication, testing and supply for
Tube Bundle – Ethane Recycle Emergency heater (11-E-114) with all materials,
consumables, tools like-to-like as per provided drawings and datasheet by
SADAF"

SABIC (Sadaf)

Jubail, KSA

October, 2019

Mining & Minerals

Boiler FW PHE Perf Measurement Instrument

Boiler FW PHE Perf Measurement Instrument

Client : MAADEN (Ma'aden Aluminium)

Prime Contractor : MAADEN (Ma'aden Aluminium)

Disciplines : Boiler FW PHE Perf Measurement Instrument

Location : Ras Al Khair, KSA

Completion : December, 2019

Scope of Work : The Project Scope includes Civil / Structural, Mechancial & Piping, Electrical & Instrumentation works

MAADEN (Ma'aden Aluminium)

Ras Al Khair, KSA

December, 2019

Petrochemicals

Pre-Fabrication, Repair & Replacement of Pipelines during VCM T/A’2019

Pre-Fabrication, Repair & Replacement of Pipelines during VCM T/A’2019

Client : SABIC (Petro kemya)

Prime Contractor : SABIC (Petro kemya)

Disciplines : Pre-Fabrication, Repair & Replacement of Pipelines during VCM T/A’2019

Location : Jubail, KSA

Completion : April, 2020

Scope of Work : The Scope include the site verification and preparation of isometric for the line to be replaced, Pre-fabrication of lines at SENDAN workshop facility, repair/ replacement of old lines and installation of new lines during VCM Plant Turnaround scheduled in October 2019. Total Dia-inches is approx. 4,000; SAFERAD and Radiography crew is considered, Hydro/pneumatic testing of lines, external sand blasting and Painting of prefabricated pipe spools and cold cutting activities.

SABIC (Petro kemya)

Jubail, KSA

April, 2020

Petrochemicals

Additional Piping, Valves and DCR Repair Services for 3EG & 3UTL during TAM 2019

Additional Piping, Valves and DCR Repair Services for 3EG & 3UTL during TAM 2019

Client : SABIC (Sharq)

Prime Contractor : SABIC (Sharq)

Disciplines : Additional Piping, Valves and DCR Repair Services for 3EG & 3UTL during TAM 2019

Location : Jubail, KSA

Completion : December, 2019

Scope of Work : "The project scope includes to piping & valves replacement, removal of existing pipe line & valves, fabrication of new pipe line as per IFC, Installation of pipe line, installation of valves, NDT & painting in SHARQ Plant
Jubail"

SABIC (Sharq)

Jubail, KSA

December, 2019

Petrochemicals

LSTK Project for Upgrade LP steam Control Valve (PV-1703) at OLF-II TA-2019

LSTK Project for Upgrade LP steam Control Valve (PV-1703) at OLF-II TA-2019

Client : SABIC (Petro Kemya)

Prime Contractor : SABIC (Petro Kemya)

Disciplines : LSTK Project for Upgrade LP steam Control Valve (PV-1703) at OLF-II TA-2019

Location : Jubail, KSA

Completion : December, 2019

Scope of Work : "The detailed SOW includes:
- Demolition of Existing 36” Pipe line 22mtrs
- Removal of 24” Isolation valve and 22” Control Valve.
- Modification of existing line and Installation of 30” Control valve.
- Supply, fabrication and installation of new line along with the insulation works
- Supply, fabrication and erection of steel structure related to modification job.
- Painting and Installation of new Control Valve and Pressure Transmitter."

SABIC (Petro Kemya)

Jubail, KSA

December, 2019

Oil & Gas

Emergency Shutdown In Gas Phase-8

Emergency Shutdown In Gas Phase-8

Client : SABIC (Gas Jubail)

Prime Contractor : SABIC (Gas Jubail)

Disciplines : Emergency Shutdown In Gas Phase-8

Location : Jubail, KSA

Completion : August, 2019

Scope of Work : "The SOW includes several activities for DCAC Chilled water distributior damage such as:
- All nozzles removal, hydro-jet cleaning, insopection & installation.
- Main distributor header disconnection, repaired, hydro-jet cleaning and installation.
- Operating pressure leak test done after above mentioned activities.
- One leaked nozzle repaired and install back. "

SABIC (Gas Jubail)

Jubail, KSA

August, 2019