Petrochemical |
Displaced Pipeline Repair and Rectify
Sector |
Petrochemical |
Project Title |
Displaced Pipeline Repair and Rectify |
Project Owner |
SABIC |
Client |
Sabtank Jubail |
Department |
PSD |
Location |
Jubail |
Start Date |
01/01/17 |
End Date |
01/07/17 |
Scope of work |
The project scope is the repair for the displaced pipelines in SABTANK and the supports rectification for the piping.
|
|
Sabtank Jubail |
Jubail |
01/01/17 |
01/07/17 |
Petrochemical |
Olefins-III TA17 Decoke Line Replacement
Sector |
Petrochemical |
Project Title |
Olefins-III TA17 Decoke Line Replacement |
Project Owner |
SABIC |
Client |
PetroKemya |
Department |
PSD |
Location |
Jubail |
Start Date |
01/01/17 |
End Date |
01/06/17 |
Scope of work |
Scope of work includes
The project scope is pre-fabrication and replacement of Decoke header in Olefins-III.
|
|
PetroKemya |
Jubail |
01/01/17 |
01/06/17 |
Petrochemical |
Electrical works for MP-EVA0-B-01-04-61 -Ethylene Pump at EVA plant.
Sector |
Petrochemical |
Project Title |
Electrical works for MP-EVA0-B-01-04-61 -Ethylene Pump at EVA plant. |
Project Owner |
SIPCHEM |
Client |
SIPCHEM |
Department |
E&I |
Location |
Jubail |
Start Date |
01/12/16 |
End Date |
01/12/16 |
Scope of work |
Scope of work includes
• Erection / dismantling of scaffolding along with existing pipe rack.
• 3 Runs, 440 meters of 3CX150mm2 power cable will be laid on existing cable tray/ladders from MCC panel to the consumer junction box.
• 1 Run, 440 meter of 5CX2.5mm2 control cable will be laid on existing cable trays/ladders from MCC panel to LCS.
• 1 Run, of 3CX150mm2 Power cable will be laid on existing cable trays./ladders from consumer junction box to the vendor junction box.
|
|
SIPCHEM |
Jubail |
01/12/16 |
01/12/16 |
Oil & Gas |
PERFORM PREVENTIVE MAINTENANCE FOR DIESEL GENERATORS
Sector |
Oil & Gas |
Project Title |
PERFORM PREVENTIVE MAINTENANCE FOR DIESEL GENERATORS |
Project Owner |
Saudi Aramco |
Client |
SWIMP Mubarraz |
Department |
SP |
Location |
Jubail |
Start Date |
01/12/16 |
End Date |
01/12/19 |
Scope of work |
Scope of Work includes:
Performing preventive maintenance in different locations in eatern region (AIWSP, QSWP and others.)
Perform preventive maintenance for Diesel Generator.
|
|
SWIMP Mubarraz |
Jubail |
01/12/16 |
01/12/19 |
Power |
Inspection and Repairing of 4 MVA Transformer at Arar Power Plant Extensıon IV Project
Sector |
Power |
Project Title |
Inspection and Repairing of 4 MVA Transformer at Arar Power Plant Extensıon IV Project |
Project Owner |
SEC |
Client |
BEST Transformer |
Department |
TNC |
Location |
ARAR |
Start Date |
01/12/16 |
End Date |
01/01/17 |
Scope of work |
Scope of Work includes
4 MVA, 4.16/0.48KV Transformer inspection, electrical testing, gasket
replacement, oil filtration and filling work & Oil Sampling and Oil Testing.
|
|
BEST Transformer |
ARAR |
01/12/16 |
01/01/17 |
Petrochemical |
Emergency Work for KV-592642 ; ASU KV Forward Plan
Sector |
Petrochemical |
Project Title |
Emergency Work for KV-592642 ; ASU KV Forward Plan |
Project Owner |
SABIC |
Client |
Ar-Razi |
Department |
PSD |
Location |
Jubail |
Start Date |
01/12/16 |
End Date |
01/12/16 |
Scope of work |
Scope of work includes
1. Unbolting of old valve, 2. Removal of old valve by Crane (160 Ton), 3.Cleaning of flange faces, 4.New valve KV-592642 mobilization from Temal workshop to site, 5.Valve KV-592642 installation by crane, 6.Gasket installation and manual bolt tightening, 7.Torquing
|
|
Ar-Razi |
Jubail |
01/12/16 |
01/12/16 |
Petrochemical |
Installation of Electrical Heat Tracing System
Sector |
Petrochemical |
Project Title |
Installation of Electrical Heat Tracing System |
Project Owner |
SADARA |
Client |
SADARA |
Department |
E&I |
Location |
Jubail |
Start Date |
01/12/16 |
End Date |
01/02/17 |
Scope of work |
Scope of work includes
1.Extension/Modification of two no. of cables after installation of PRVs in existing pipeline
2. Removal & Reinstatement of heat tracing cable & termination from 8 nos of new
PRVs
|
|
SADARA |
Jubail |
01/12/16 |
01/02/17 |
Petrochemical |
2EG/2UTL Piping and Valves Job Package TAM 2017
Sector |
Petrochemical |
Project Title |
2EG/2UTL Piping and Valves Job Package TAM 2017 |
Project Owner |
SABIC |
Client |
SHARQ |
Department |
PSD |
Location |
Jubail |
Start Date |
01/11/16 |
End Date |
01/06/17 |
Scope of work |
Scope of work includes
Piping, Pre-Fabraction, Scaffolding, Marking, cutting and Replacement of the Affected pipe portion according to isometric drawings, steam trap, affected vent, replacement of the sealant box for ethylene line drain, bevling of new piping by pass, Removing & replacement of Isolation valves, Welding & Installation of piping & valves, NDT, Hydrotesting & Commissioning.
|
|
SHARQ |
Jubail |
01/11/16 |
01/06/17 |